Saturday, November 1, 2008

Trailer

The trailer was the 1st construction task. I have just uncovered some photos taken during construction. It was made from 100*50*5 steel with the main draw bar from 100*100. On the delivery trip down from NSW with the boat on we actually hit 120kmh. The whole unit was a breeze to tow. We hardly knew it was on ...until we looked in the mirror.

Finished trailer minus guards. The all up trailer weight was 600kg for registration purposes.


Nice welds. I left the section open firstly for galvanising & secondly to make sure that the frame dries out.



This is the dual axle spring set up



A forklift makes life easier. So does a mate who is a boilermaker by trade.

Relocation

Unfortunately I have outstayed my welcome at the factory I am in & will have to relocate. The only low cost monetary option is to bring it home, the high cost of that will be the flak from the war department...oh well.
So I have spent most of the time working out the logistics of the move. I have been storing the trailer at another location so it will be good to get it back & fit the hull to. An advantage to being at home is that I will be able to bits & pieces more often. Hopefully it will not be overshadowed by the problem mentioned earlier.

Sunday, October 26, 2008

Mast

I have been looking at the mast slung high above me in the factory & was a bit worried that prior to purchasing it had been stored outside & was suffering from a bit of corrosion.
So i decided to check it out. To my surprise it cleaned up very well with some water & a good working over with a green scouring pad.
I cut off a portion to use as a mould for the composite spreaders that i am going to make. So I am happy in that I do not have to buy another mast.
I have not started on the spreaders yet, but , will document progress as I go.



There are still some small imperfections that will need to be cleaned up. At least I know that it will clean up well enough for anodising. I have found an anodiser in Melbourne that can handle 11mtrs.

Friday, October 24, 2008

Chainplates

I decided to make the chainplates with some self made carbon fibre tube. To do this I found a piece of aluminium tube that was about 12.5mm OD.
I wrapped this with peel ply then added about 4 layers of wet glass followed by 3 layers of carbon uni. Then i tightened the whole unit by twisting it tight onto the aluminium mandrel. Once i was happy with this i bagged it & put the vacuum pump on.


A 12mm pin fits well inside this. From there I proceeded as normal with the chainplates.

Anchor Well drain flanges

While fiddling the other day I decided to make some flanges to cover the exit holes on either side of the hull.
I cut 2 pieces of poly pipe on an angle & taped them down to the table. Then placed some peel ply, followed by 4 layers of glass & another layer of peel ply. Smoothed it all down flat to get excess resin out. Here is the result before i cleaned them up.




Sunday, October 19, 2008

Beams



When i purchased the boat the beams were made apart from fitting the tops. That is good because at least i can see what is inside them. I have decided that i am going to fit the beams to the boat before i put the tops on. There are 2 reasons for this. Firstly i am not confident that the brackets that are fitted to the beams are actually level. Secondly, i can get a good level from the inside base & am planning on using a laser level to true it all up. This way i can glue all the brackets in place & if there any adjustments to be made they can be done before the lids go on.
I have drilled all the bolt holes for the beam brackets & have noticed that the base they are on is not level, so i have levelled them off with bog.

Wednesday, October 15, 2008

Parts

I was quite amazed at how much extra gear was included. Some of it I will not be using, but a lot will be of use.


Complete mast base